When is a right-of -way permit required?

Anytime work is being performed in the right-of-way; whether it's maintenance work or new construction; private utility or public utility or similar activities within an easement. A permit is always required when making a new connection to a City of Troy water main, sanitary sewer or storm sewer regardless of the location of the utility, even if it is in your backyard.

Why is a right-of-way permit required?

To ensure that the work performed is done in accordance with the City of Troy's standard specifications; that the public infrastructure is not compromised; inconveniences to the public are minimized; and disturbed areas are restored to original or better condition.

Who should obtain a right-of-way permit?

It is highly recommended that the person or contractor performing the work obtain the permit. A home owner can pull a permit for a contractor if they are willing to assume the risk and liability for the contractors work.

What is needed to obtain a right-of-way permit?

  1. A completed and signed application.
  2. A map, plan and/or specification of the proposed facility.
  3. Traffic plan in cases of work impacting a public road.
  4. Proof of insurance with the City of Troy as an Additional insured.
  5. The appropriate surety bond or cash deposit along with the permit inspection fees. Fees are calculated by the Engineering Department after review of the application.

Where to obtain a right-of -way permit?

The Engineering Department is located on the first floor City Hall building 500 W. Big Beaver. Applications can be emailed to ParsonsJM@troymi.gov or faxed to 248-524-1838 for preliminary review and fee calculation. Final submittal requires an original signed application with fees, surety, insurances and plans mailed or delivered to the Engineering Department.

For additional information contact the Engineering Department at 248-524-3383.